Project Schedules

Gosfield Wind Project

 

October 2010 • Full commercial operation

Comber Wind Project

 

Winter/Spring 2011 • Detailed engineering work, final permitting, contracting and planning

• Construction of access roads, widening of intersections in preparation for   turbine deliveries and foundation installation

• Substation and electrical cabling
Spring/Summer 2011 • Turbine component delivery and installation
Fall 2011 • Project commissioning




image
image
image