Project Schedules

Gosfield Wind Project


Spring/Early Fall 2009 • Detailed engineering work/td>
Winter 2010 • Opening of street-front community office
Fall 2009 • Start-up of Community Liaison Group
Fall 2009/Winter 2010 • Construction of access roads and foundations
June 2010 • Turbine and major component delivery
Summer 2010 • Installation of turbines
• Individual turbine start-up and commissioning
Fall 2010 • Full commercial operation

 

Comber Wind Project

Spring/Summer 2010 • Planning meetings with landowners
• Surveying; geotechnical investigations; archeological studies
• Access road and electricity collection system design
• Construction planning
• Fox snake habitat investigation; fish studies
• Drainage permits; municipal construction permits
Fall 2010• Construction start: access roads, intersection upgrades
Winter/Spring 2011• Turbine foundations; substation; electrical cabling
Spring 2011• Turbine component delivery
Spring/Summer 2011• Turbine installation
Fall 2011 • Project commissioning